#: 21
Project: Blast Furnace No.3 Loading unit
Direction: Automation
Customer: Public Joint Stock Company "Zaporizhstal"
Automation object/equipment: Schneider Electric Quantum Unity Pro
Work performed: Participation in commissioning of the equipment and software of the software and hardware complex of automated process control system
Start: 2017
End: 2017
Work Status: Completed
#: 22
Project: Khorostkov Sugar Factory Modernization of CHP plant equipment
Direction: Automation
Customer: LLC «Radekhovsky Sakhar»
Automation object/equipment: Generator Unit 6300V 6MW Basler AVR DECS-250
Work performed: Engineering, software development, equipment supply, commissioning for the modernization of the synchronous generator excitation and auto-synchronization system
Start: 2017
End: 2017
Work Status: Completed
#: 23
Project: Khorostkov Sugar Factory Modernization of CHP plant equipment
Direction: Automation
Customer: LLC «Radekhovsky Sakhar»
Automation object/equipment: Turbo generator Т-6-2У3 Simatic S7
Work performed: Engineering, software development, equipment supply, commissioning works for modernization of the regulation system for turbo generator and grandmasters of the CHPP
Start: 2017
End: 2017
Work Status: Completed
#: 24
Project: Kozovsk sugar factory Modernization of CHP plant equipment
Direction: Automation
Customer: LLC «Radekhovsky Sakhar»
Automation object/equipment: Turbo generator Т-6-2У3 Simatic S7
Work performed: Engineering, software development, equipment supply, commissioning works for modernization of the regulation system for turbo generator and grandmasters of the CHPP
Start: 2017
End: 2017
Work Status: Completed
#: 25
Project: Zbarazh sugar factory Modernization of CHP plant equipment
Direction: Automation
Customer: LLC «Radekhovsky Sakhar»
Automation object/equipment: Turbo generator TG-6/3000 Simatic S7
Work performed: Engineering, software development, equipment supply, commissioning works for modernization of the regulation system for turbo generator and grandmasters of the CHPP
Start: 2017
End: 2017
Work Status: Completed
#: 26
Project: Kryviy Rig TPS Monitoring of technological parameters of power units, station No.1-10
Direction: Automation
Customer: Public Joint Stock Company "DTEK Dniproenergo"
Automation object/equipment: Power units, station No.1-10 Simatic S7
Work performed: Engineering, software development, equipment supply, installation works, commissioning works
Start: 2017
End: 2017
Work Status: Completed
#: 27
Project: Rivne NPP, station No.3 power unit Monitoring of vibration condition
Direction: Automation, Software
Customer: Public Joint Stock Company "ENERGOATOM" LLC "Promvitech"
Automation object/equipment: Turbo generator station No.5, Feed electric pump -1, Feed electric pump -3 Vibration condition monitoring system Vibrovizor, Simatic S7
Work performed: Engineering, software development, equipment delivery, commissioning
Start: 2016
End: 2017
Work Status: Completed
#: 28
Project: Kyiv CHP Plant-6 Onshore Pumping Station
Direction: Automation electrical
Customer: Public Joint Stock Company "Kyivenergo" LLC «Remhydromash»
Automation object/equipment: Automation of pumping station, frequency-regulated drive SINAMICS, Simatic S7
Work performed: Engineering
Start: 2016
End: 2017
Work Status: Completed
#: 29
Project: Pumping station Lift No.3 Pump unit District heating pump -4, Control board
Direction: Automation
Customer: KP DOR "Aulskiy Vodovod"
Automation object/equipment: Automation of pumping station, turbo gear unit VOITH, Simatic S7
Work performed: Engineering
Start: 2016
End: 2016
Work Status: Completed
#: 30
Project: Slavyansk TPP
Direction: Electrical engineering
Customer: Public Joint Stock Company "Donbassenergo"
Automation object/equipment: Uninterruptible Power System СЕ+Т
Work performed: Equipment supply
Start: 2016
End: 2017
Work Status: Completed